- Preparation (3D plans and asking permission to the local government)
- 3D Design (3D plan for myself to get an idea of what could fit in)
- Furniture (First ideas how the furniture should look like)
- Drilling (Drilling holes in the backyard for the poles of the foundation)
- Poles (Filling the holes with concrete to form the poles)
- Digging (Digging a big hole for the basement and shortening the pole)
- More digging (Digging even deeper and shortening the poles even more)
- Water (At maximum depth now, just hitting the ground water level)
- Foundation (Construction of the foundation of the basement)
- Steel (Construction of the steel work for the walls)
- Walls (Construction of the walls)
- Roof (Construction of the roof)
- Wiring (Putting electrical wiring in the roof and walls.
- Door (Demolition of the side of our house)
- Ventilation (The basement is ready, and I can breath down there)
- Stairs (Basement finished and the first time we could go down ourselves)
- Isolation (Putting on some isolation and making it waterproof)
- Heating (Putting in the pipes for the floor heating system)
- Demoistering (Getting all the moisture out of the walls)
- Cabling (Installing the cable guiding system)
- Floor (Putting the final layer of the floor)
- Garden (Finished construction and putting our garden back in place)
Vector Deep Dive : Hybrid Systems
19 hours ago
4 comments:
The project looks great, it must have been a real experience creating it!?
Yes it was a big adventure. I'm glad it is over though.
I'm so very excited to see that after the completion of it.
Thank you. It is a nice place to work now :)
Post a Comment